Projects: Rowley Regis Connected
-
Investment£1,500,000 consisting of 100% Towns Fund
-
Timeline
Start: June 2022
Delivery: April 2025
-
LocationSelected sites within Rowley Regis
The Rowley Regis Connected project will generate a multi phased set of multi-modal infrastructure improvements to link transport (rail, bus) and employment hubs in Blackheath, Cradley Heath and Oldbury.
The project will deliver new pedestrian and cycle routes including segregated cycle routes, resurface and widen footpaths, upgrade crossing facilities, introduce traffic calming, upgrade lighting, improve signage and road markings.
The project Full Business Case was approved by Government in March 2022. The project team have since undertaken a number of activities in the background to finalise the work packages to deliver this project.
Deliverables: | Status: |
10 Temporary Full Time jobs supported during project implementation | To be achieved by April 2025 |
2km resurfaced/improved roads | To be achieved by April 2025 |
2km new cycle ways | To be achieved by April 2025 |
0.28km new pedestrian paths | To be achieved by April 2025 |